November 28

Details staring to be added, the underside of the roofing is going on
in part because not all the needed materials for the top part were ordered together.
Eventually it will get out to the worksite and put into place.


Here are the metal sheets for the top side of the roof, but again, they need to wait.
we do a lot of waiting
and waiting
and waiting